Emaar Palm Hills possession delayed? What Haryana RERA ordered.

Buyers in Palm Hills, Gurugram, have taken Emaar to the Haryana RERA, and the Authority's orders show what they got.

CaseMinister, India's most advanced legal AI, is trained on the judgements of district courts, consumer commissions and tribunals, including RERA, as well as the Supreme Court and High Courts.

What the Authority has ordered against Emaar

  • Interest for every month you waited

    From the possession date in your agreement until Emaar made a valid offer of possession, backed by an occupation certificate.

  • Charges you should not have paid

    Charges taken before possession, or charges the agreement did not provide for.

  • Your money back, with interest

    Where the flat was not delivered and the buyer chose to withdraw from the project.

How CaseMinister helps with your flat

1

Tell us about your flat

  • Your project and the possession date in your agreement
  • What Emaar has offered or charged you
  • In your language, typed or as a voice note
  • Upload your supporting documents, if any
2

We prepare your report

  • We go through each Haryana RERA case on your Emaar project, one by one
3

Know where you stand

  • What buyers like you were awarded, and what was refused
  • How they claimed, which papers they used, and what Emaar said back
  • Decide your next step. Ask CaseMinister anything about your report, any time, on WhatsApp or the website

An order on Palm Hills

Haryana RERA · Order · 2025
Project
Palm Hills, Sector 77, Gurugram
What was asked
Delay in flat possession
What the Authority found
The Authority found that possession of the flat was delayed beyond the contractual due date.
What it ordered
It directed EMAAR MGF Land Developers Limited to pay interest on the actual paid-up amount for the specified delayed period, and disposed of the complaint.
The buyer's name and unit are left out.

Orders on Palm Hills

Project names are shown. What was ordered is in the full orders.

Every order on your project: what buyers asked for, what Emaar argued, what the Authority decided, and what it means for your flat.

Questions buyers ask

Has Emaar been ordered to pay delay interest on Palm Hills?

Yes. In a 2025 order on Palm Hills, the Authority directed Emaar to pay interest for the delay in possession. Your report shows the orders closest to your flat.

How do I get the Palm Hills orders?

Tap "Get the report for my flat" and tell us your possession date. We go through each Haryana RERA case on Palm Hills and send the report to your WhatsApp.

Find out what you can claim

Tell us your project and possession date, and we'll prepare the report for your flat. Or ask a question on WhatsApp first.

Get the report for your flat

We'll prepare it from the Haryana RERA orders on your project and send it to your WhatsApp.

Your number is used only for your report and replies to you.