State of Gujarat v. Dahyabhai Zaverbhai

Supreme Court of India · 24 February 1997 · [1997] 2 S.C.R. 469

Court
Supreme Court of India
Decided
24 February 1997
Case no.
C.A. No. 1821 of 1997
Reported as
[1997] 2 S.C.R. 469
Result
Appeal(s) allowed
Bench
K. Ramaswamy, G.T. Nanavati
Length
3 pages
Have a question about this judgment?

Ask our Legal AI about it on WhatsApp: free, no signup, in English or Hindi.

Write it first.

PETITIONER:
STATE OF GUJARAT
Vs.
RESPONDENT:
DAHYABHAI ZAVERBHAI
DATE OF JUDGMENT: 24/02/1997
BENCH:
K. RAMASWAMY, G.T. NANAVATI

ACT

HEADNOTE

JUDGMENT

ORDER

Delay condoned.

Leave granted. We have heard learned counsel on both sides.

This appeal by special leave arises from the judgment of the Gujarat High Court, dated August 21, 1995 passed in First Appeal No.3875/95.

Admittedly the respondent-contractor had entered into an agreement No.B-1/17 of 1981-82 to complete the work of protective measures for the road bridge across river Ambica. The appellant had issued the work order on June 3, 1981. It is true that there was a delay in handing over the work sheet and the specifications. But the trial Court after considering the entire evidence had noted its finding thus:

"In the present case the land on

which the construction work was

required to be made was a land of

the Government and not of private

party or private owner, so there

was no hurdle in the construction

work of the plaintiff but the

plaintiff himself has left the

construction and hence, in the

present case, only the plaintiff

can be held a person who has

revoked the contract. Before

revoking the contract, the

plaintiff was given sufficient time

and reasonable opportunity to

complete the work but the plaintiff

has not done anything to complete

the work and left the work and the

sit so we have no option, the

deft/Department to take the

decision for revocation of the

contract."

In view of the above finding, the inevitable conclusion is that the respondent had abandoned the execution of the work in spite of the opportunity having been given to him to complete the work. Clause 3 of the Contract reads as under:

"Clause-3: In any case, in which

under any clause or clauses of this

contract the contractor shall have

rendered himself liable to pay

compensation amounting to the whole

of his security deposit (whether

paid in the sum or deduction by

instalments) or in the case of

abandonment of the work owing to

serious illness or death of the

contractor or any other cause,

Executive Engineer, on behalf of

the Government of Gujarat shall

have power:-

(a) to rescind the contract(of

which recession notice in writing

to the Contractor under the hand of

the Executive Engineer shall be

conclusive evidence) and in that

case the security deposit of the

Contractor shall stand forfeited

and be absolutely at the disposal

of Government.

That in view of this express

provision the Hon’ble High Court

erred in holding that the

petitioner/State is not entitled to

forfeiture the deposit."

A reading thereof would clearly indicate that in any case, under any clause or clauses of the contract, the contractor would have rendred himself liable to pay compensation amounting to the whole of his security whether paid in the sum or deducted by instalments; in the case of abandonment of the work owing to serious illness or death of the contractor or any other cause, the Executive Engineer is empowered to have the contract rescinded; in that case the security deposit of the contractor shall stand forfeited and be absolutely at the disposal of the Government. In consequence, forefeiture of the security deposit, on account of abandonment of the work by the appellant, was perfectly valid. The High Court, therefore, was not right in directing the appellant to refund the security deposit. Learned counsel for the respondents contends that time was not the essence of the contract and therefore, the recession of the contract was not for valid reason. We are, however, not on the validity of the recession of the contract but on the question whether the respondent had abandoned the contract or not. The question in that backdrop arises: whether the recession of the contract was correct in law? In view of the above facts, the action was legal. In that perspective, the ratio in M/s Hind Construction Contractors v. State of Maharashtra [A.I.R. 1979 SC 720] has no relevance. Therein , the contract was not rescinded. Work was executed after the extended time and the claims were made before the Arbitrator for the work done during the extended time. Therein, the contention was raised that time was essence of the contract. Respondent and the contractor having not complete the work within the schedule time, he was not entitled to the amount under the award. In that contract, this Court had held that time was not essence of the contract. That question, however, does not arise in this case for the reason that the respondent had abandoned the contract.

The appeal is accordingly allowed. No costs.

Ask CaseMinister about State of Gujarat v. Dahyabhai Zaverbhai

Your 24×7 legal assistant on WhatsApp answers with the judgments that apply, in English or Hindi. No signup needed.

Questions about this judgment, or a case like it?Ask on WhatsApp