CaseMinister
CaseMinister › Judgments › Supreme Court › 2019 › Power Grid Corporation of India v. Tamil Nadu Generation and

Power Grid Corporation of India v. Tamil Nadu Generation and Distribution Co. Ltd. and Ors. Etc.

Court
Supreme Court of India
Decided
9 May 2019
Case no.
C.A. No.-000684-000684 - 2007
Bench
The Chief Justice, Mohan M. Shantanagoudar
Author
The Chief Justice

In short. The case involves a dispute regarding the apportionment of Foreign Exchange Rate Variation (FERV) between debt and equity in the context of tariff regulations for electricity transmission. The Supreme Court of India reviewed the decision of the Appellate Tribunal for Electricity, which had allowed the apportionment of FERV only concerning debt liability. The court upheld the Tribunal's decision, concluding that the apportionment of FERV is not mandated by existing regulations and is not a substantial question of law.

Facts

The appeal arises from decisions made by the Central Electricity Regulatory Commission (CERC) concerning the capitalization of FERV. The CERC's orders dated June 30, 2003, and December 4, 2003, were challenged, leading to a review by the Appellate Tribunal for Electricity, which issued a judgment on October 4, 2006. The appellant, Power Grid Corporation of India, is a transmission company responsible for the conveyance of power, with tariffs set by the CERC. The core issue is the methodology for apportioning FERV after it has been calculated and added to the capital cost.

Arguments

Petitioner Arguments

The appellant argued that FERV should be added to the overall capital cost and subsequently apportioned between debt and equity based on a normative debt-equity ratio. They contended that this practice has been followed historically and is essential for fair tariff determination. The court, however, found that the argument lacked substantial legal backing, as the relevant regulations did not mandate such apportionment.

Respondent Arguments

The respondents, represented by Tamil Nadu Generation and Distribution Company, countered that the Electricity Regulatory Commissions Act, 1998, was designed to eliminate such practices of apportioning FERV. They cited specific regulations that allow for the recovery of FERV directly from the appellant without necessitating its capitalization. The court agreed with the respondents, noting that the regulations do not support the appellant's claims.

Precedents considered

The judgment did not cite specific precedents but referenced the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2001, particularly Regulation 1.13(a), which pertains to the calculation of FERV rather than its apportionment. The court emphasized that the methodology for calculating FERV was not in dispute.

Legal principles

The court considered the principles of regulatory compliance under the Electricity Regulatory Commissions Act, 1998, and the Tariff Regulations, 2001. It highlighted that the apportionment of FERV is not a legal requirement and that the existing regulations do not provide for such a division post-calculation.

Decision and reasoning

Rationale

The court reasoned that the issue of apportioning FERV between debt and equity does not constitute a substantial question of law. It clarified that the regulations cited by the appellant do not support their position, and the historical practice they referred to is not legally binding. The court's analysis focused on the regulatory framework rather than the appellant's claims of customary practice.

Outcome

The Supreme Court upheld the Appellate Tribunal's decision, affirming that FERV should only be apportioned concerning debt liability and not equity. The court did not provide specific instructions for an appeal process, as the matter was resolved in favor of the respondents.

Conclusion

This judgment reinforces the regulatory framework governing electricity tariffs in India, clarifying that the apportionment of FERV is not a legal requirement. It underscores the importance of adhering to established regulations and the limitations of customary practices in regulatory matters.

Read the full judgment on the Supreme Court website (PDF)

Ask CaseMinister about Power Grid Corporation of India v. Tamil Nadu Generation and Distribution Co. Ltd. and Ors. Etc.

Find the judgments that followed or distinguished it, with the paragraph relied on in each. Two answers free on WhatsApp, no signup.