CaseMinister
CaseMinister › Judgments › Supreme Court › 1971 › Commissioner of Commercial Taxes, Mysorebangalore v. Hindust

Commissioner of Commercial Taxes, Mysorebangalore v. Hindustan Aeronautics Ltd.

Supreme Court of India · 17 December 1971

Court
Supreme Court of India
Decided
17 December 1971
Bench
Sikri, S.M. (Cj), Bhargava, Vishishtha, Dua, I.D., Khanna, Hans Raj, Mitter, G.K.
Length
8 pages
Have a question about this judgment?

Ask our Legal AI about it on WhatsApp: free, no signup, in English or Hindi.

Write it first.

PETITIONER:
COMMISSIONER OF COMMERCIAL TAXES, MYSOREBANGALORE
Vs.
RESPONDENT:
HINDUSTAN AERONAUTICS LTD.
DATE OF JUDGMENT17/12/1971
BENCH:
SIKRI, S.M. (CJ)
BHARGAVA, VISHISHTHA
DUA, I.D.
KHANNA, HANS RAJ
MITTER, G.K.
CITATION:
1972 AIR 744 1972 SCR (2) 927

ACT

Sales Tax-Contract for manufacture and supply of railway coaches-if sale or Works-contract.

HEADNOTE

The correspondence between the Railway Board and the respondent (assessec regarding the terms and conditions for the manufacture and supply of railway coaches, and the indemnity bond in respect of the contract, disclosed that,. (i) The Railway booked capacity of the assessee for the purpose of construction of railway coaches; (ii) an advance, on account, was made to the extent of 90% of the value of the material on the production of a certificate by the inspecting authority. (iii) the material used for the construction of coaches before its use was the property of the railway; (iv) there was no possibility of any other material being used for the construction, and (v) the words used in the contract were, ’manufacture and supply of the following coaches.’ On the question whether there was a sale of railway coaches liable to sales tax. or only a works-contract, HELD : The answer to the question whether a contract is a works contract or a contract of sale depends upon the construction of the terms of the contract in the light of surrounding circumstances. [935 A-B] (1) In the present case. when all the material used in the construction of a coach belonged to the Railways there cannot be any sale of the coach itself. It was a pure works-contract, the difference between the price of a coach and the cost of material being only the cost of service rendered by the assessee. [935 G-H] (2) Whether the wheels-sets and under frames were supplied free of cost or not makes no essential difference, [936 A-B] (3) The material and wage escalator and adjustments regarding final price mentioned in the contract are neutral factors. [935G] State of Gujarat v. Kailash Engineering Co., 19 S.T.C. 13 (S.C.) followed.

JUDGMENT

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 710 of 1968. Appeal from the judgment and order dated March 1, 1967 of the Mysore High Court in Sales Tax Appeal No. 8 of 1966. 928 Somanatha Iyer, R. B. Datar and M. S. Narasimhan, for the appellant. S. T. Desai, Mrs. A. K. Verma, J. B. Dadachanji, O. C. Mathur and Ravinder Narain, for the respondent. B. Sen, Santosh Chatterjee, G. S. Chatterjee and P. K. Chakravarti, for intervener No, 1. D. Goburdhun, for intervener No. 2. The Judgment of the Court was delivered by Sikri, C.J. In this appeal by certificate granted by the High Court of Mysore the only question involved is whether the deliveryby the respondent-Hindustan Aeronautics Ltd.-hereinafter referred to as the assessee-to the Railway Board of railway coaches model 407, 408 and 411 is liable to sales tax under the Central Sales Tax etc. The Commercial Tax Officer, by assessment order dated March 28, 1964, in respect of the assessment year 1958-59, included the turnover in respect of the supply of these coaches. The Sales Tax Officer rejected the contention of the assessee that therewas no sale involved in the execution of the works-contract inview of certain decisions of the High Courts; e.g., McKenzievLimited v. The State of Bombay(1) and Jiwan Singh v. State of Punjab (2). In appeal, the Deputy Commissioner of Commercial Taxes confirmed the order. In revision the Commissioner of Commercial Taxes also came to the same conclusion. He observed:

"The contracts specifically mentioned that the

under-frame shall always remain the property

of the Railway Board. On the other hand, the

order placed with the assessee company here

was for the ’manufacture and supply’ of

railway coaches. The payment to the assessee

company is specifically referred to as

’price’. The conditions normally included in

contracts for works are absent in this order."

He further observed :

". . . I would like to reiterate here that

even the actual contract is for manufacture

and supply of rail coaches. There is no

mention that the rail coaches are to be

constructed on the underframes of the

indentor ........ If it was really a works

contract the under- (1) 13 S.T.C. 602. (2) 14 S.T.C. 957. 929

frames would have been made available for

construction instead of being ’supplied free

of cost’ and the indentor’s lien on them would

have been made clear. The plain meaning of

the contract is that the underframes were

transferred to the assessee company free of

cost by the Railway Board and that after

construction of rail coaches on them, the rail

coaches were sold to the Railway Board at the

agreed price. The agreement does not also

contemplate any inspection in the course of

execution as would normally be provided for in

a works contract. The only inspection is

after completion and at Perembur." He thought that case of the assessee in respect of model 411 railway, coaches was Worse. Regarding the financial arrangement between the Railway Board and the assessee, he observed

"The Railway Board made only advance payments

for purchase of materials and did not itself

procure the material and supply them to the

assessee company. The condition that the

materials become property of the Railway Board

as and when purchased is only for purposes of

providing adequate security for the advances.

In the circumstances, the materials can be

deemed to be hypothecated to the Railway Board

and the advance payments are really part

payment of the final price. The transaction

relating to Rail coaches of model 411 is

clearly a sale." He, therefore, confirmed the appellate order of the Deputy Commissioner. The assessee then took an appeal to the High Court of Mysore under s. 24(1) of the Mysore Sales Tax Act read with s. 9(3) of the Central Sales-tax Act. The High Court was not satisfied with the material on record and directed that a report be sent on three points, viz :

"(i) Whether and if so to what extent the

assessee has drawn advance payment from the

Railway Board in respect of the material

utilised for completing the contracts in

question;

(ii) Whether any material, in respect of

which no advance have been drawn, has been

utilised by the assesseefor completing the

contracts; and

(iii) Whether the assessee has used for

completing the contracts any material not

specifically procured for the, purposes of

completing the contracts." 930 The Commercial Tax Officer submitted his report, and certain extracts may be reproduced below :

"My findings revealed that as and when they

purchased materials, they sent to the Railway

Board ’an invoice’ accompanied by a list of

the details regarding the materials purchased.

90 per ’cent of the value of these materials

was then paid to the company after inspection

of the materials by the board’s representa-

tive. Invoice No. 31009 of 15-10-1956 is

obtained as a sample. This invoice shows that

materials for the value of Rs. 2,60,374-12-0

were purchased by the company for 407 model

coaches. The details of the materials are

given in list attached to the invoice. The

invoice and the list were sent to the board

with a covering letter dated 15-10-1956 asking

payment of Rs. 2,34,517-4-0 being 90 per cent

of the invoice amount. The amount of this

invoice is included in the Board’s remittance

note No. 1290 of 30-10-1956 and a cheque was

issued to the company for the total of several

such invoices. The amount of the cheque

received on 30-10-1956 was Rs. 22,90,719-0-O."

He concluded :

" (1) It is not possible to specify the exact

amount received from the board as advance

payments. It is said that the

construction was spread out more than one year

and a running, account was maintained showing

the debits and credits for this coaches.

(2) It is said that no materials, for which

advance was not drawn, was utilised for

building the coaches.

(3) It is not possible to find out whether

any materials not specifically procured for

the construction of coaches were used. But it

is said that there is no possibility of any

other materials being used for this

construction. The constructions are said to

be done at particular shed which is separately

located. No other work is undertaken in this

section. All the materials procured for

constructions of coaches are said to be kept

separately in this section alone. Materials

not connected with this work are not mixed up

with the materials in this section. Separate

stock registers are maintained for this

section. Receipts and issues of materials for

the constructions of coaches are being

accounted for in this register under code

numbers." 931 The High Court allowed the appeal and set aside the order including the turnover relating to the construction of railway coaches, models 407, 408 and 411. Facts found by the High Court and as they appear to us are as follows On February 3, 1955, the Ministry of Railways wrote to the Hindustan Aircraft Ltd. regarding the coaching programme 1955-56. The letter reads :

"In order to book your capacity, construction

of the following is planned on your works

against the 1955-56 R.S.P. 1. Third Class Coaches B.G. model 407

120 2. Military Coaches ’M’ type model 408

60

Total :180

The intention of this intimation is to

facilitate such arrangements as you may find

necessary for provising for materials and for

planning capacity for the question. You

should therefore treat this as a firm booking

of your capacity." After discussions and settlement of terms between officers of ,the Government of India and of the assessee, the Railway Board placed orders with the assessee. The terms agreed between the parties are found stated in a letter of the Government of India, Ministry of Railways (Railway Board) No. 57/147/RE(163) dated May 4, 1957. This relates (to the first of the models 407. We may extract some portions of the letter. It is stated thus

In continuation of their letter No.

56/142/’3/Re dated 8-1-57 the Railway Board

are pleased to place an order on your work for

the manufacture and supply of the following

coaching stock on terms and conditions stated

under para 2 below :- Item No. Description of stock Particular Nos. Price per

coach of Rly specification Required (without wheels Board’s and Drawing and axlesand Rolling No. under-frames) Stock Programme 1957-58 384 Broad Gauge 55-B-14 180 Rs. 94,731/-

Class III (Provisional)

Coaches fully CSC 1119

furnished to

model ’407’ 932 Following terms and conditions are relevant: (i) Price

(a) The price mentioned above is for stock

without wheels and axels and underframes, and

is provisional. Final price will be settled

by negotiations after you have submitted your

claim for the coaches ordered on you up to

1954-55 Rolling Stock Programme on the basis

of the wages and material escalator approved

by the Board.

(b) The final price when settled shall be

subject only to the Standard Wages and

material escalator clauses given below........

(c) The final payment on completion of this

order shall be subject to examination and

check of your books by the Chief

Administrative Officer, Integral Coach

Factory, Perambur, Madras.

(ii) Wheelsets and Underframes

The Wheelsets and Underframes for the stock

will be supplied to you free of cost f.o.r.

your work siding.

(iv) Delivery

The delivery of the above stock f.o.r. your

works siding is required to commence after the

completion of the stock ordered on your works

against 1956-57 R.S.P. and required to be

completed by January 1957, or earlier.

(v) Inspection Authority

The inspection of this stock shall be carried

out by a representative (C.M.E. Southern

Railway) before the coaches are despatched.

(vi) Terms of payment

(a) Advance ’on account’ payment to the

extent of 90% of the value of the materials

shall be made to you on receipt of materials

and on production of a certificate from the

Inspecting Authority.

(b) Payment of full contract price, less ’on

account’ payment already will be made on deli-

very of coaches in complete condition and good

working order, duly certified by the

Inspecting

933

Authority on the lines of procedure laid down

vide Board’s letter No. 57/142/6/M dated 4-2-

1952 (Copy enclosed).

(vii) Other terms of Contract.

(i)..................

(ii) If and when sales tax on this order

becomes payable under law, such payments, when

made, will not be on your account. The

Railway will not, however, be responsible for

payment of the sales tax paid by you under

misapprehension of law. There is an indemnity bond in respect of this contract and we may set it out fully.

"1. Standing Indemnity for advance payment

against contract relating to Railway Board’s

order for construction and delivery of all

metal III class B.G. coaches now pending under

orders Nos. 52-142/4/M dated 16th February,

1952 and 53/142/4/M dated 3rd March, 1953 and

against contracts in respect of future orders

that may be given by the Railway Board from

time to time, by the Hindustan Aircraft Ltd.,

Bangalore represented by General Manager

hereinafter called the Company in favour of

the President of Union of India. lie Hindustan

Aircraft Ltd., hereby undertake to hold at

their works at Bangalore for and on behalf of

the President of the Union of India, and as

his property in trust for him the Stores and

articles in respect of which advances are made

to them under Railway Board’s letters, No .

52,/142/4/M dated 16th February, 1952 and

53/142/4/M dated 3rd March, 1953 and hereafter

to be made to the Company under future orders

from the Railway Board from time to time.

2. The said stores and articles shall be

such as are required of the purpose of the

pending and future contracts and the advances

made and to be made are without prejudice to

the provisions of the contract as to rejection

and inspection and any advance made against

stores and articles rejected or found

unsatisfactory on inspection shall be,

refunded immediately to the President of the

Union of India.

3. The Company shall be entirely

responsible for the safe custody and

protection of the said articles and stores

against all risks till they are duly delivered

to the 12-L736Sup-CI/72 934 .lm15 President of the Union of India or as he may direct and shall indemnify the President of the Union of India against any loss, damage or deterioration whatsoever in respect of the said stores and articles while in our possession. The said articles and material shall at all times to be open to inspection of any officer authorised by Government. 4. Should any loss of damage occur or a refund become due, the President of the Union of India shall be entitled to recover from the Company compensation for such loss or damage or the amount to be refunded without prejudice to any other remedies available to him by deduction from any sum due or any sum which at any time hereafter may become due to the Company under this or any other contract." We have set out the terms of the Indemnity Bond in great detail because the learned counsel for the appellant has strongly relied on the terms thereof. The text of the invoice sent by the assessee for the purpose of receiving 90% advance may be seen from the covering letter dated October 15, 1956 relating to one of the invoices. The letter reads :

"On account payment of 90% on material pro-

cured for rail coaches-407 and 408 model VI

order. Further to our letter No. Al/Inv/1 169

dated 8-10-56 enclosing our invoice for Rs.

42,892-15-0 we enclose herewith our invoice

No. 31009 dated 15-10-1956 in duplicate for

Rs. 2,34,517-4-0 being 90% of materials

procured in October 1956. Kindly arrange

payment of the invoice alongwith the invoice

already sent. Please instruct your resident

representative to check the stock of materials

as per lists attached to our invoices and send

them to the Deputy Financial Adviser and Chef

Accounts Officer, Integral Coach Factory,

Perambur, so that he may send his represen-

tative to check the value of the materials." On these facts we have to decide whether there has been any sale of the coaches within the meaning of the Central Sales Tax Act. We were referred to a number of cases* of this Court and the High Courts, but it seems to us that ultimately the answer must-depend upon the terms of the contract. The answer to the (1) 16S.T.C.518-McKenziesv.State of Maharashtra. (2) [1965] 2S.C.R.782-Patnaik & Co. v. State of Orissa. 935 question whether it is a works contract or it is a contract of sale depends upon the construction of the terms of the contract in the light of the surrounding circumstances. In this case the salient features of the contract are as follows : (1) The Railway books capacity of the assessee for the purpose of construction of railway coaches. (2) Advance on account is made to the extent of 90% of the value of the material on the production of a certificate by the inspecting authority. (3) The material used for the construction of coaches before its use is the property of the Railway. This is quite clear from para I of the Indemnity Bond set out above. No other meaning can be given to the words in the bond to the effect that "the Hindustan Aircraft Ltd. hereby undertake to hold at their works at Bangalore for and on behalf of the President of the Union of India and as his property in trust for him the Stores and articles in respect of which advances are made to them." It seems to us clear that the property in the materials which are used for the construction of the coaches becomes the property of the President before it is used. (4) It seems that there is no possibility of any other material being used for the construction as is borne out from the report written by the Commercial Tax Officer. (5) As far as the coaches of models 407 and 408 are concerned, the wheelsets and underframes are supplied free of cost. (6) In the order the words used are "manufacture and supply of the following coaches." (7) The material and wage escalator and adjustments which are mentioned in the contract are neutral factors. On these facts it seems to us that it is a pure works contract. We are unable to agree that when all the material used in the construction of a coach belongs to the Railways there can be any sale of the coach itself. The difference between the price of a coach and the cost of material can only be the cost of services rendered by the assessee. If it is necessary to refer to a case which is close to the facts of this case, then this case is more in line with the decision of 936 this Court in State of Gujarat v. Kailash Engineering Co.(1) than any other case. The only difference as far as coach model No. 41 1 is concerned is that in that case the wheelsets and underframes are not supplied free of cost but otherwise there is no essential difference in the terms. This does not make any difference to the result. In the result the appeal fails and is dismissed with costs. V.P.S. Appeal dismissed. (1) 19 S.T.C. 13. 937

Ask CaseMinister about Commissioner of Commercial Taxes, Mysorebangalore v. Hindustan Aeronautics Ltd.

Your 24×7 legal assistant on WhatsApp answers with the judgments that apply, in English or Hindi. No signup needed.

Questions about this judgment, or a case like it?Ask on WhatsApp