Chairman, Board of Mining Examination &another v. Ramjee

Supreme Court of India · 3 February 1977 · [1977] 2 S.C.R. 904

Court
Supreme Court of India
Decided
3 February 1977
Reported as
[1977] 2 S.C.R. 904
Result
Disposed of
Bench
Krishnaiyer, V.R.
Length
7 pages
Have a question about this judgment?

Ask our Legal AI about it on WhatsApp: free, no signup, in English or Hindi.

Write it first.

PETITIONER:
CHAIRMAN, BOARD OF MINING EXAMINATION &ANOTHER
Vs.
RESPONDENT:
RAMJEE
DATE OF JUDGMENT03/02/1977
BENCH:
KRISHNAIYER, V.R.
GUPTA, A.C.
CITATION:
1977 AIR 965 1977 SCR (2) 904
1977 SCC (2) 256

ACT

Coal Mines Regulations--Regulation 26--Interpretation of.

Rules of natural justice---Concept of reasonably oppor-

tunity cannot be fitted into a rigid mould--Need for a

strict liability---Code for subterranean occupations.

HEADNOTE

Under regulation 26(1) if, in the opinion of the Regional

Inspector, a person to whom an Overman’s, Sirdar’s,

Engine-driver’s, Shot-firer’s, or Gastesting Certificate has

been granted is incompetent or is guilty of negligence or

misconduct in the performance of his duties, he may, after

giving the person an opportunity to give a written explana-

tion, suspend his certificate by an order in writing. U/r

26(2) he shall within a week of such suspension report the

fact to the Board together with all connected papers includ-

ing the explanation, if any received from the person con-

cerned. U/r 26(3) the Board may, after such inquiry as it

thinks fit, either confirm or modify or reduce the period of

suspension of the certificate, or cancel the certificate.

The respondent, a shot-firer in a colliery, violated the

provisions of the Coal Mines Regulations by entrusting his

risky, technical work to an unauthorised person which re-

sulted in an accident injuring one Bhadu. The Regional

Inspector u/r 26(1) gave him an opportunity for an explana-

tion in writing and after considering the materials before

him forwarded the papers to the Chairman of the Board

together with a recommendation for cancellation of the cer-

tificate under Regulation 26(3). The Board bestowed its

judgment on the materials gathered which included the delin-

quent’s admission, and cancelled the shot-firing certifi-

cate. The High Court allowed the writ petition assailing

the orders of cancellation of the licence and held: (1) The

Board had no jurisdiction since the Regional Inspector did

not suspend the certificate first before reporting (2) The

Regional Inspector had no power to recommend but only to

report and so the Board’s order influenced by the recommen-

dation was bad in law and (iii) the Board should have given

a fresh opportunity to be heard before cancellation of the

certificate and its absence violated natural justice, void-

ing the order.

Accepting the Court,

HELD: (1 ) Law is meant to serve the living and does not

beat its abstract wings in the jural void. Its functional

fulfilment as ’social engineering’ depends on its scruti-

nized response to situation, subject-matter and the complex

of realities which require ordered control. A holistic

understanding is simple justice to the meaning of all legis-

lations. Fragmentary grasp of rules can, n misfire or even

backfire, as in this case. [906 H, 907 A]

(2) The judicial key to construction is the composite

perception of the daha and the dahi of the provision. To be

literal in meaning is to see the skin and miss the soul of

the Regulation. [909 A-B]

(3) Over-judicialisation can be subversive of the justice

of the law. To invalidate the Board’s order because the

Regional. Inspector did not suspend the certificate is a

fallacy. The Board’s power is independent and is ignited by

905

the report, which exists in this case, of the Regional

Inspector. There is an overall duty of oversight vested in

the board to enforce observance of rules of safety. [909 D]

(4) To set aside the order on the ground that the Re-

gional Inspector had no power to recommend but only to

suspend and report that his recommendation influenced the

Board’s order is to enthrone a processual nicety do dethrone

plain justice. Suspension, on a.n enquiry, predicates a

prior prima-facie finding of guilt and to make that known to

the Board implicitly conveys a recommendation. The differ-

ence between suspension plus report and recommendatory

report is little more than between Tweedledum and Tweedledee

Recommendations are not binding but are merely raw materials

for consideration. Where there is no surrender. of judge-

ment by the Board to the recommending Regional Inspector,

there is no contravention of the cannons of natural justice.

[909 E-F, 910D-E]

(5) Natural justice is no unruly horse, no lurking land

mine, nor a judicial cure-all. If fairness is shown by the

decision-maker to the man proceeded against, the form

features and the fundamentals of such essential processual

propriety being conditioned by the facts and circumstances

of each situation. no breach of natural justice can be

complained of. Unnatural expansion of natural justice.

without reference to the administrative realities and other

factors of a given case, can be exasperating.

Courts cannot look at law in the abstract or natural justice

as a mere artifact. Nor can the), fit into a rigid mould the

concept of reasonable opportunity. If the totality of cir-

cumstances satisfies the Court that the party visited with

gelverse order has not suffered from denial of reasonable

opportunity the Court will decline to be punctilious or

fanatical as if the rules of natural justice were sacred

scriptures. In the instant case, the Board cannot be anath-

ematised as condemning the man without being heard. The

respondent has, in the form of an appeal against the report

of the Regional Inspector, sent his explanation to the

Chairman of the Board. He has thus been heard dad compli-

ance with Regulation 26 in the circumstances is complete.

[909G-H, 910 A-G]

Tereaesai’s case [1970] 1 S.C.R 251; Management of DTU

[1973] 2 S.C.R. 114: Tandon’s case [1974] 4 SCC 374 referred

to.

Observations: Sensitive occupations demand stern juristic

principles to reach at scapegraces, high and low, and not

mere long drawn-out commissions whose verdicts often prove

dilatory ’shelter’ for the men in whom Parliament his en-

trusted plenary management. Any sensitive jurisprudence of

colliery management must make it cardinal to pt nish the

Board vicariously for any major violations and dreadful

disasters, on macro:considerations of responsibility to the

community. The Board must quit, as a legal pendry, if any

dreadful deviation. deficiency, default or negligence

anywhere in the mine occurs. This is a good case for new

principles of liability, based on wider rules of sociologi-

cal jurisprudence to tighten up the law of omission and

commission at the highest levels. Responsibility and penal-

ty must be the concomitants of highly-paid power vested in

the top-brass. Any deviance on the part of these high-

powered authorities must be visited with tortious or

criminal liabilities. [908 F-H, 907 D-FI

(The Court emphasised the need for evolving a code of strict

liability calling to utmost care not only the crowd of

workers and others but the few shall care or quit so that

subterranean occupations necessary for the nation are made

as risk-proof as technology and human vigilance permit).

JUDGMENT

CIVIl, APPELLATE JURISDICTION: Civil Appeal No. 2294

1968.

Appeal from the Judgment and Order dated 25-9-1967 of the

Madhya Pradesh High Court in Misc. Petition No. 595/66.

L.N. Sinha, Sol. Genl, B. Datta and Girish Chandra for the

Appellants.

906

S.K. Gambhir, amicus curiae, for the Respondent.

The Judgment of the Court was delivered by

KRISHNA IYER, J.--If the jurisprudence of remedies were

understood and applied from the perspective of social effi-

caciousness, the problem raised in this appeal would not

have ended the erroneous way it did in the High Court.

Judges must never forget that every law has a social pur-

pose and engineering process without appreciating which

justice to the law cannot be done. Here, the socio-legal

situation we are faced with is a colliery, an explosive, an

accident, luckily not lethal, caused by violation of a

regulation and consequential cancellation of the certificate

of the delinquent shot-firer, eventually quashed by the High

Court, for processual solecisms, by a writ of certiorari.

We may state at the outset that the learned Solicitor

General agreed that the appellant, the Board of Mining

Examination, would be satisfied if the law, wrongly laid

down by the High Court, were set aside and declared a right

and he was not insisting on the formal reversal of the order

affecting the respondent (who is unrepresented before us).

We proceed on that footing.

The few necessary facts may be narrated to bring up the

legal issue in its real setting.

The respondent was a shot-firer in a colliery and being

a risky, technical job, had to possess a certificate for it.

He handed over an explosive to an unskilled hand who fired

it, an accident occurred and one Bhadu, employed in the

mine, was injured. The Regional Inspector of Mines imme-

diately enquired into the cause of the accident and

found, on the respondent’s virtual admission, qualified by

some prevarication, that the shots were fired not by himself

but by a cutter, an unauthorised person for shot-firing to

whom the respondent had wrongfully entrusted the work.

Thereby he contravened the relevant Coal Mines Regulations.

The Regional Inspector gave him an opportunity for explana-

tion and, after considering the materials before him, for-

warded the papers to the Chairman of the Board together with

a recommendation for cancellation of the certificate under

Reg. 26. The Board bestowed its judgment on the materials

gathered by the Regional Inspector at the enquiry, which

included the delinquent’s admission, and cancelled the

shot-firing certificate. The said cancellation was shot down

by a writ of the Court on the ground of violation of Reg.

26.

Was Regulation 26, in the context and set. tin. g of the

Mines Act, misinterpreted by the High Court at all? This is

the short question canvassed before .us. We permit our-

selves a few observations Which serve as perspective-set-

ters. Law is meant to serve the living and does not beat

its abstract wings in the jural void. Its functional

fulfilment as social engineering depends or its sensitized

response to situation, subject-matter and the complex of

realities which require

907

ordered control. A holistic understanding is simple justice

to the meaning of all legislations. Fragmentary grasp of

rules can misfire or even backfire, as in this case. It is

a notorious fact that collieries--Indian collieries, both

before and after nationalisation-are strategic sources of

the nation’s fuel and, operationally, areas of tragic human

hazards. We need coal, we want miners to bring it from the

bowels of the earth. The dangerous technology is not yet so

perfect in India as to ensure risk-free extraction. And,

after many lives have been lost by the neglect of operatives

or supervisors or supine bosses, follows the scenario of

tears and torn-down homes, a little monetary compensation, a

flutter in Parliament, a longdrawn-out Commission, a

routine Report about lapses and recipes and the little man’s

life-or death lot continuing to receive callous considera-

tion at the hands of the law, law-matter,

law-enforcer---this sombre colliery disaster sequence must

educate and inform the jurisprudence of high-risk opera-

tions. In short, the Mines Act (and Regulations) must

receive its judicial construction in the total setting,

teleclogically approached, not fragmentarily dissected. The

relevant regulation is only a tiny inset in the larger

justice of the statute.

The Mines Act has a scheme designed to avoid accidents

and ensure safety. A system of certificates, supervisions

and penalties is part of this scheme. The broad responsi-

bility for due enforcement of the Act rests on the Board and

the relevant regulation casts liabilities on the lesser men.

Any sensitive jurisprudence of colliery management must make

it cardinal to punish the Board vicariously for any major

violations and dreadful disasters, on macro considerations

of responsibility to the community. The Board must quit, as

a legal penalty, if any dreadful deviation, deficiency,

default or negligence anywhere in the mine occurs. In the

present case a microbreach is being punished, but when major

mishaps occur the top echelons, on account of inadequacies

in colliery codes, escape and make others the scapegoats.

Although, in this ease, only injury, not death, has oc-

curred, there is a good case for new principles of liabil-

ity, based on wider rules of sociological jurisprudence,

to tighten up the law of omission and commission, at the

highest levels. Responsibility and penalty must be the

concomitants of highly-paid power vested in the top-brass.

Back to the pedestrian statement of facts. The re-

spondent’s curious contention, accepted by the learned

Judge, is best understood after reading Regulation 26:

"26. Suspension of an Overman’s, Sir-

dar’s, EngineDriver’s, shot-firer’s, or

Gas-testing Certificate--

(1) If, in the opinion of the Regionl

Inspector, a person to whom an Overman’s,

Sirdar’s, Engine-driver’s, Shot-firer’s, or

Gas-testing Certificate has been granted ii

incompetent or is guilty of negligence or

misconduct in the performance of his duties,

the Regional Inspector may, after giving the

person an opportunity to give a written expla-

nation, suspend his certificate by an order in

writing.

10--206SC1/77

908

(2) Where the Regional Inspector has

suspended a certificate under sub-regulation

(1) he shall within a week of such suspen-

sion report the fact to the Board together

with all connected papers including the expla-

nation if any received from the person

concerned.

(3) The Board may, after such inquiry as

it thinks fit, either confirm or modify or

reduce the period of suspension of the certif-

icate, or cancel the certificate."

The plain purpose of the regulation is to pre-empt further

harm by suspending the certificate of the shot-firer ’if in

the opinion of the Regional Inspector’ he ’is incompetent

or is guilty of negligence or misconduct in the performance

of his duties... after giving the person an opportunity to

give a written explanation’. This suspension is itself a

punishment liable to confirmation, modification, reduction

of the period of suspension or, by way of enhancement, can-

cellation of the certificate by the Board. Before taking

such action by way of cessation, as it were, the Board gets

a report from the Regional Inspector of the fact of

suspension and makes ’such enquiry as it thinks fit’. In

the present case, the Board had an explanation (styled

an appeal) from the respondent, and also a recommendation by

the Regional Inspector for cancellation of the certificate.

The latter had not suspended the delinquent but had merely

hold an enquiry, reached the prima facie view of guilt and

and instead of suspension at once, only made a recommenda-

tion to the Board for cancellation.

The Regional Inspector has, among his statutory duties,

the supervision of the observance of the safety rules and

the holding of enquiries (see sections 7 & 14). He has to

report to the Board on breaches of regulations and condi-

tions. The Board, in its turn, has the over-all charge of

the safe management of the mine. Derelictions and viola-

tions must reach its vigilant eye and be visited with

prompt action. Jurisprudentially speaking, there is need to

cast an obligation on the Board and the higher inspectorate

not to be negligent, indifferent or insoucient in the

discharge of its overall responsibility which includes

anticipation of likely mishaps and introduction of the

latest measures to promote safety for the men working in the

dark depths at the mercy of the wicked mood of Yama. Any

deviance on the part of these high-powered authorities must

be visited with tortious or criminal liability. Such is the

price which high position must pay for the consequences of

calamitous failures. Sensitive occupations demand stern

juristic principles to reach at scapegraces, high and low,

and not mere long-grown-out commissions whose verdicts often

prove dilatory ’shelter’ for the-men-in whom Parliament has

entrusted plenary management. We emphasize this matter to

awaken the law-makers to evolve a code of strict liability

calling to utmost care not only the crowd of workers and

others but the few who shall care or quit so that subterra-

nean occupations necessary for the nation are made as risk-

proof as technology and human vigilance permit..

909

Unfortunately, the High Court surrendered to nar-

rowness of interpretation of Regulation 26 by accepting the

submission of the respondent. To be literal in meaning is

to see the skin and miss the soul of the Regulation. The

judicial key to construction is the composite perception of

the deha and the dehi of the provision. So viewed, Reg. 26

is easy of comprehension.

The High Court held that the order of cancellation

was illegal for a few reasons which strike us as untenable.

The argument runs thus. Without first suspending the cer-

tificate, the Regional Inspector cannot report to the Board

and without such a report following upon a suspension the

latter cannot take seisin of the matter. Since the Region-

al Inspector did not suspend the respondent, the Board had

no jurisdiction. Secondly, the Regional Inspector had no

power to recommend, but only to report and so the Board’s

order, influenced by the recommendation, was bad in law.

Thirdly, the Board should have given a fresh opportunity to

be heard before cancellation of the certificate and its

absence in the present case violated natural justice, void-

ing the order.

All the three points serve to warn the courts how

over-judicialisation can be subversive of the justice of the

law. Now, how can the cancellation order by the Board be

bad for failure to suspend the certificate by the Regional

Inspector ? The Board’s power is independent and is ignited

by the report of the Regional Inspector. Such a report

exists here. There is an overall duty of over sight vested

in the Board to enforce observance of rules of safety. To

invalidate the Board’s order because the Regional Inspector

did not suspend the certificate is a fallacy.

Now to the next point. The vice that vitiates the

Board’s order is stated to be the recommendation contained

in the Regional Inspector’s report. Had he suspended and

reported, he would have been in order. But suspension, on

an enquiry, predicates a prior prima facie finding of guilt

and to make that known to the Board implicity conveys a

recommendation. The difference between suspension plus

report and recommendatory report is little more than

between Tweedledum and Tweedledee. And to set aside an

order on such a ground is to enthrone a processual nicety to

dethrone plain justice.

The last violation regarded as a lethal objection is

that Board did not enquire of the respondent, independently

of the one done by the Regional Inspector. Assuming it to

be necessary, here the respondent has, in the form of an

appeal against the report of the Regional Inspector, sent

his explanation to the Chairman of the Board. He has thus

been heard and compliance with Reg. 26, in the circum-

stances, is complete. Natural justice. is no unruly horse,

no lurking land mine, nor a judicial cure-all. If fairness

is shown by the decision-maker to the man proceeded against,

the form, features and the fundamentals of such essential

processual propriety being conditioned by the facts and

circumstances of each situation, no breach of natural

justice can be complained of. ’Unnatural expansion

910

of natural justice, without reference to the administra-

tive realities and other factors of a given case, can be

exasperating. We can neither be finical nor fanatical but

should be flexible yet firm in this jurisdiction. No man

shall be hit below the belt--that is the conscience of the

matter.

Shri Gambir, who appeared as amicus curiae and indus-

triously helped the Court by citing several decisions bear-

ing on natural justice, could not convince us to reach a

contrary conclusion. It is true that in the context of Art.

311 of the Constitution this Court has interpreted the

quality and amplitude of the opportunity to be extended to

an affected public servant. Certainly we agree with ’the

principles expounded therein. But then we cannot look at

law in the abstract or natural justice as a mere artifact.

Nor can we fit into a rigid mould the concept of reasonable

opportunity. Shri Gambhir cited before us the decisions in

Teredesai(1); Management of DTU(2) and Tandon(3); and

one or two other rulings. The ratio therein hardly mili-

tates against the realism which must inform reasonable

opportunity’ or the rule against bias. If the authority

which takes the final decision acts mechanically and without

applying its own mind, the order may be bad, but if the

decision-making body, after fair and independent considera-

tion, reaches a conclusion which tallies with the recommen-

dations of the subordinate authority which held the prelim-

inary enquiry, there is no error in law. Recommendations

are not binding but are merely raw material for considera-

tion. Where there is no surrender of judgment by the Board

to the recommending Regional Inspector, there is no contra-

vention of the canons" of natural justice. We agree with

Shri Gambhir that the adjudicating agency must indicate in

the order, at least briefly why it takes the decision it

does unless the circumstances are so clear that the conclud-

ing or decretal part of the order speaks for itself even

regarding the reasons which have led to it. It is desirable

also to communicate the report of the Inquiry Officer,

including that part which relates to the recommendation in

the matter of punishment, so that the representation of the

delinquent may be pointed and meaningful.

These general observations must be tested on the con-

crete facts of each case and every miniscule violation does

,not spell illegality. If the totality of circumstances

satisfies the Court that the party visited with adverse

order has not suffered from denial of reasonable opportunity

the Court will decline to be punctilious or fanatical as if

the rules of natural justice were sacred scriptures.

We are satisfied that the order of the Board cannot be

anathematised as condemning the man without being heard.

The appeal, on the point of law, must be allowed but, in

the light of the concession made, as stated earlier, we

leave the formal order of the High Court undisturbed. No

costs.

S.R. High Court orders main-

tained.

(1) [1970] 1 S.C.R. 251.

(2) [1973] 2. S.C.R. 114.

(3) [1974] 4 S.C.C. 374.

911

Ask CaseMinister about Chairman, Board of Mining Examination &another v. Ramjee

Your 24×7 legal assistant on WhatsApp answers with the judgments that apply, in English or Hindi. No signup needed.

Questions about this judgment, or a case like it?Ask on WhatsApp