Unpaid invoices, a contract bill held back, or a bank recovery suit? See how Delhi's commercial courts decided recent cases, then ask CaseMinister about yours.
CaseMinister, India's most advanced legal AI, is trained on the judgements of district courts, consumer commissions and tribunals, including RERA, as well as the Supreme Court and High Courts.
District courts, Delhi · 2026Decreed
Recovery of delayed municipal contractor bill
The Municipal Corporation paid the contractor's principal bill while the case was pending, but the payment had been delayed beyond the six-month period allowed for a bill below Rs.5 lakhs. The court therefore decreed interest at 9% for the delay from 27.03.2025 to 23.01.2026, with further interest if the decreetal amount was not paid within eight weeks.
District courts, Delhi · 2026Decreed
Recovery of unpaid trade goods
The plaintiff supplied electrical goods to the defendant, who made some payments but left Rs.3,85,845/- outstanding. Because the defendant did not challenge the plaintiff's evidence in cross-examination or present defence evidence, the Court passed a decree for the principal amount, 9% interest subject to the stated exclusion, and costs.
District courts, Delhi · 2026Decreed
Recovery of commercial goods payment
Neo-Hy Laminates Pvt. Ltd. proved that decorative laminate materials were supplied and that Rs.8,03,015/- remained unpaid. The court rejected the allegations of defective goods and the alleged settlement document, and decreed the principal amount with 9% annual interest from filing of the suit, plus costs.
District courts, Delhi · 2026Decreed
Recovery of government contractor bills
Against Municipal Corporation Of Delhi
A municipal contractor sued for unpaid amounts under a work order. The court found that the main running bill had been paid during the case, but the withheld amount and security amount remained unpaid, and it awarded those amounts with 9% interest and costs.
District courts, Delhi · 2026Decreed
Bank loan recovery
Canara Bank sued to recover the balance of a term loan taken by the deceased husband of one defendant. The court found that the wife had acknowledged the debt and decreed Rs.4,87,883.82 with 11.30% annual interest and costs against her, while holding that the guarantor was not liable.
District courts, Delhi · 2026Partly allowed
Recovery of money under a government construction contract
Against Municipal Corporation of Delhi
The construction firm claimed unpaid bill and security amounts from the Municipal Corporation of Delhi. The court rejected those claims because the work was delayed, the alleged cause of delay was not proved, and no written extension request was shown, but directed payment or release of any differential GST amount.
Summaries of orders read by CaseMinister. Names of private persons are left out.
AskAny legal question, in English or Hindi. The answer names the judgements behind it.
Cases like yoursSee how this forum decided cases with facts like yours, and why.
DraftYour complaint, application or reply, drafted from your facts and documents.
TrackAdd your case once. See the next hearing date and the latest order.
WhatsAppCall, send a voice note, message, or forward any document, 24x7.
Questions
Can CaseMinister help with my case in Delhi?
Yes. Tell CaseMinister what happened, or upload your FIR, notice or order. CaseMinister answers from how Delhi's courts have decided cases like yours, and names the judgements behind the answer.
Can CaseMinister draft for me?
Yes. Applications, replies and notices are drafted from your facts and documents. Edit the draft before you file.
Can I track my case?
Yes. Add your case number or CNR once and see the next hearing date and the latest order.